Geothermal project Aardwarmte Vierpolders

Drilling of a geothermal doublet in Vierpolders
After an extensive period of project preparations the drilling rig was moved to Vierpolders in July 2015. Two J-shape directional wells were drilled from the same location at ca. 5m read more »

Drilling a sidetrack using a Hydraulic Workover Unit

Since September 2014 the production of the well was hampered due to a blockage. Various investigations were performed, among one by Well Engineering Partners, to find the cause of this blockage. Based on this study a repair plan was made, which involved read more »

BAS-3O sidetrack

Well project in Pietersbierum, the Netherlands, 21 January 2015
Out of Frisia Zout BV’s BAS-3 a side-track was succesfully drillled & completed to establish a new salt production cavern. read more »

Final abandonment BAS-3 salt cavern

Well project in Pietersbierum, the Netherlands, June 2014
Frisia Zout BV’s salt production cavern BAS-3 was successfully permanently abandoned (final abandonement) in September 2014. This was following temporary plugging of the well read more »

De Lier, drilling for geothermal energy update

August 2014, De Lier, The Netherlands
Well Engineering Partners (WEP) has successfully completed the well construction of two wells for the geothermal doublet for GDL (V.O.F. Geothermie De Lier) in De Lier, The Netherlands. The wells have been read more »

Operations have commenced on FRISIA BAS-3

Pietersbierum, 5th of June 2014
Operations have commenced on the well BAS-3 . BAS-3 is a well of Frisia Zout BV, part of ESCO.
Firstly the current cavern will be abandoned, requiring the placement of a seal in the bottom part read more »

De Lier, drilling for geothermal energy

May 2014, De Lier, the Netherlands
Tuesday 20th of May the drilling of the geothermal doublet for V.O.F. Geothermie de Lier has started by spudding the first well LIR-GT-01. Drilling contractor is KCA Deutag using its T-49 rig.
The doublet read more »

3 well interventions at NEDMAG by snubbing unit

December 2013 - February 2014, NEDMAG salt solution mining, Veendam , the Netherlands
Well Engineering Partners completed successfully three Hydraulic Workover Snubbing Operations (HWO). In the 7 weeks, 2 wells were brought back into production read more »